What is being renovated? One room? A whole home? Are you doing a gut renovation? A partial? Just a bathroom? Are you saying “renovation” but really mean “decoration?”
Here are some guidelines that may help (all time frames are estimated):
Furniture, window treatments or wall coverings: most take a minimum of 4-6 weeks to order. Custom work and foreign ordering can take up to 20 weeks. If you want to choose your own fabrics, add 2-4 weeks to allow yourself or your designer to shop, help you make your selections and arrange for materials to be forwarded to the manufacturing firm.
Custom closets or built-ins: From design to installation, approximately 2-8 months, depending on your choices
Bathroom Renovation: From design to putting your toothpaste on the sink, approximately 8-12 weeks. Actual time for demolition and construction, approximately 4-6 weeks.
Kitchen Renovation: From design to putting your dishes away, up to 20 weeks. Actual time for demolition and construction, approximately 4-6 weeks.
Refresh your studio or one-bedroom apartment: (no heavy construction, some furniture, possibly some built-ins), approximately 3-9 months, depending on your choices
Gut Renovate your studio or one-bedroom apartment: (new walls, new kitchen and bath,electrical work, some or all new furniture) approximately 5-9 months, depending on your choices
Refresh your two-bedroom apartment: (no major construction, some furniture, possibly some built-ins or a bathroom upgrade), approximately 5-12 months, depending on your choices
Gut Renovate your two-bedroom apartment: (new walls, new kitchen and bath rooms, electrical work, all new furniture), approximately 9-18 months, depending on your choices